GMP Electronic Dust-free Workshop Purification Project Case

Today we are going to share a case of purification engineering of an electronics company. The purification project is mainly for the purification and renovation of workshop and air-conditioning room, with a total construction area of ​​5769 square meters.

 

In the project, the interior partition walls and ceilings are made of machine-made rock wool gorgeous color steel plate and 50mm-thick machine-made glass magnesium color steel plate, and the ceiling height is 2.6m. The workshop floor adopts epoxy resin self-leveling floor and 2mm anti-static self-leveling floor. The ground is not only smooth and beautiful, but its antistatic effect is lasting and effective!

 

According to the national standard of GMP clean room design and HVAC design. The workshop has a GMP clean room with a purification level of 100,000. The workshop temperature should be controlled at 22~26°C, and the humidity should be controlled at 50%~60%. The workshop needs to use ultraviolet sterilization system, and the main air conditioner room on the roof is 180RT. The workshop air supply adopts 3 sets of constant temperature and humidity purification air-conditioning fan cabinets, and the ventilation duct area is 2772 square meters. Equipped with high-efficiency air outlet with 500~1500 air volume. Provide a ventilated and comfortable working environment for workshop production.

 

The purification project was successfully completed in the end, and the construction period was more than a week shorter than expected. The successful completion of the project ahead of schedule is inseparable from the designer's overtime work and staying up late to catch up with the design drawings and the full cooperation of the construction site team. Finally, the feedback information returned by the electronics company indicated that after the completion of the work, the docking process was more careful and cautious, and the construction process and post-commissioning indicators were all qualified.

 